New Detached ADU in Westwood Lakes, FL: What It Takes and What It Costs
A new detached ADU in Westwood Lakes runs $90,000 – $220,000 for a full standalone unit (our project range here lands $45,000 – $130,000 on the smaller end of that band), and it typically takes 6 to 10 months from permit submittal to final inspection. The single biggest cost drivers are unit size, whether you need a full second utility service, and how much of the site has to be raised or drained before a slab goes down. Call (888) 418-7102 and we’ll walk your lot with you and put a real number in writing.
How We Build a Detached ADU in Westwood Lakes, Step by Step

Here’s the honest sequence, with the durations we see on Westwood Lakes lots. Every stage has a decision attached to it, so read this before you commit to anything.
- 1
Stage 1: Lot walk and feasibility (week 1 – 2). We measure setbacks, find the septic or sewer lateral, and check the flood zone and impervious-area limits on your parcel. You decide the footprint and where the unit sits relative to the main house, the driveway, and the property line. This is where most surprises surface, so we get it done first.
- 2
Stage 2: Design and permit submittal (weeks 3 – 12). We finalize the floor plan, the structural package, and the wind-load calculations, then submit to Miami-Dade County’s Department of Regulatory and Economic Resources. You approve finishes and fixtures during this window so nothing stalls later. County review is where timelines stretch, and plan review corrections are common.
- 3
Stage 3: Site prep and foundation (weeks 13 – 18). Clearing, grading, and raising the pad if the water table demands it. Then the monolithic slab, with anchor bolts and hold-downs set for the wind rating. You decide drainage direction and where the utility trench runs.
- 4
Stage 4: Framing, envelope, and MEP rough-in (weeks 19 – 28). Concrete block up, roof trusses tied down, impact openings set, then plumbing, electrical, and HVAC roughed in for inspection. You sign off on the rough-in inspection schedule so the county visits line up with our crew’s sequence.
- 5
Stage 5: Finishes and final inspection (weeks 29 – 40). Drywall, flooring, cabinetry, fixtures, paint, and the final certificate of occupancy. You do the walkthrough with us, we fix the punch list, and the unit is ready to rent or house family.
This is the whole job end to end, and honestly it’s a big one. If you’re weighing a detached unit against a smaller attached option, our Home Additions & ADU in Westwood Lakes page covers the wider scope so you can compare fairly.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make on a New Detached ADU in Westwood Lakes
The build itself is mostly fixed by code. The finishes and systems are where your money and your taste actually go to work, so here’s what you’re picking between and the honest trade-off on each.
- Unit size and layout. A 400 – 500 sq ft studio is the cheapest per square foot because it shares one wet wall and one HVAC zone. Push to 700 – 800 sq ft with a separate bedroom and you add a second zone, more foundation, and more roof, which is where budgets climb. Decide your square footage before you fall in love with a floor plan.
- Metal roof vs. shingle. Standing-seam metal costs more up front but handles wind uplift and Miami-Dade’s salt air better on a small roof. Architectural shingles are cheaper and fine when the pitch and underlayment are right. On a detached unit the roof area is small, so the metal upgrade is usually worth pricing.
- Impact-rated windows and doors. The county requires them, so this isn’t optional. You’re choosing between hurricane-rated vinyl and aluminum frames, and between fixed and operable units. Fixed units cost less and seal better; operable give you ventilation when the power’s out. ActiveYards and similar brands make rated exterior products if you’re tying the unit to a fence or gate.
- Flooring. Porcelain tile handles the humidity and flooding risk best. Luxury vinyl plank is warmer underfoot and cheaper, but it doesn’t love standing water. Wood is the wrong call in a flood zone unless you’re set on it and willing to accept the risk.
- Utilities. A full second electrical service with its own meter is cleaner for renting but costs more. Tapping the main panel is cheaper if it has capacity, and older Westwood Lakes panels often don’t.
What a New Detached ADU Costs in Westwood Lakes, FL

Full detached ADU construction in Westwood Lakes runs $90,000 – $220,000, and the smaller configurations we build here land in the $45,000 – $130,000 band. That’s the honest spread because ADUs vary enormously in size and site conditions. Here’s what moves the number from the low end to the high end:
- Square footage. A 450 sq ft studio sits near the bottom. A 900 sq ft two-bedroom pushes past $180,000 on its own.
- Site and drainage work. Westwood Lakes sits on flat, low-lying ground with a high water table, so filling and raising the pad, plus drainage swales, can add real money. A lot that drains well saves you thousands.
- Utility upgrades. A new electrical service, a sewer tap, or a separate water meter each add cost. Tying into existing service saves, if the existing service is up to it.
- Material grade. Kitchen and bath finishes, flooring, and impact-window frame choice swing the total by $15,000 or more between builder-grade and premium.
- Permit scope. A full ADU with a certificate of occupancy requires plan review, wind-load engineering, and multiple inspections. A simpler structure is cheaper to permit but limited in what you can do with it.
Every written estimate we hand you is line-item, so you can see exactly where the money goes. The promotions that apply to projects like this are straightforward: $1,000 off projects over $10,000, a free project estimate and design consult, and 0% financing for 18 months. Nothing gets added later without your sign-off.
See the difference
Before
After
Before
After
Before
AfterWhat Westwood Lakes Homes Specifically Do to This Job
Westwood Lakes was built out almost entirely between the late 1950s and the 1970s, which means nearly every lot here already has a house on it and often a converted garage, an enclosed carport, or a past addition that was never permitted. When you go for a detached unit, those existing conditions come into play. Miami-Dade County’s inspectors are known for flagging unpermitted past work during even minor renovation reviews, so it’s better to know about it now than at final inspection. Permits here run through the county’s Department of Regulatory and Economic Resources, not a city hall, and the plan review is thorough.
The climate piece matters too. Westwood Lakes sits on flat, low-lying ground with a high water table, so a detached ADU here needs an elevated pad, reinforced garage doors if you’re adding a carport, and impact-rated windows to meet Miami-Dade’s wind-borne debris and floodplain requirements. Summer downpours and hurricanes are the reason this page leads with resilience rather than square footage. If your unit needs its own driveway approach, homeowners often pair this with Concrete Driveways & Concrete Work in Westwood Lakes to keep the water moving away from the new slab, or a Paver Driveways in Westwood Lakes if they want a finished look. We cover the whole Westwood Lakes area and the ZIP 33165 corridor, so the lot walk is easy to schedule.
Serving Westwood Lakes, FL – Our Local Coverage Area
We serve Westwood Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Westwood Lakes

Six to ten months from permit submittal to certificate of occupancy is the realistic window. Most of that is plan review and inspection scheduling with Miami-Dade County, not construction itself, which is roughly four to five months of actual building. Call (888) 418-7102 and we’ll give you a timeline based on your specific lot.
Yes. A new detached ADU requires a building permit and plan review through Miami-Dade County’s Department of Regulatory and Economic Resources. There’s no legal path to skipping it, and unpermitted work will surface at resale or during any future remodel. We pull the permits and manage the inspections.
No, because a detached unit can’t share plumbing or electrical with the main house without trenching new lines across the yard. A detached ADU always needs its own supply lines, drain lines, and typically its own panel. That’s part of why detached costs more than an attached unit. An attached layout can sometimes reduce that work, and our Home Additions & ADU team can walk you through both.
Plan on $90,000 – $220,000 for a full detached unit, with smaller configurations in the $45,000 – $130,000 range. The biggest swing factors are size, site drainage, and utility upgrades. Call (888) 418-7102 for a line-item estimate – the consult is free.
Every ADU project is covered by our 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If something’s not right, we come back and make it right. Calls are answered by a live person 24/7, so you’re never waiting until Monday to reach someone.
Get a Free Estimate for Your Detached ADU in Westwood Lakes
We’ll walk your lot, talk through size and site options, and give you a written, line-item estimate for a new detached ADU in Westwood Lakes. No pressure to commit, no hidden numbers. Call (888) 418-7102 to schedule it, and a real person will pick up to book your visit.