This page is about the site work and utility connections that make an accessory dwelling unit possible in Sunset, FL, not the design or the build itself. If you’re pricing that scope, expect $45,000 – $130,000 for ADU Site Prep & Utilities in Sunset, depending on lot conditions, run distances and how much of the existing service has to be upgraded. Call (888) 418-7102 for a free on-site estimate before you commit to a number.
Most of the site and utility package runs four to eight weeks of actual work, but it sits inside a longer permit clock. The variables that move it – lot drainage, distance to the meter, soil, and whether the panel has room – are all things we read on a walkthrough, not on a phone call.
What ADU Site Prep & Utilities in Sunset actually covers
Site prep and utilities is the unglamorous half of an ADU: clearing and grading the build pad, getting power, water and sewer to the unit, and passing the inspections that prove it was done to code. In Sunset, that work runs into Miami-Dade’s post-Andrew building standards, which is why the utility trench and the slab details get scrutinized harder here than in most of the country.
Our technicians have up to 12 years of experience on this kind of work, and every project carries the 730-Day Done Right Promise – if it’s not done right, we make it right.
- Realistic total timeline: 6 – 14 weeks from permit approval to final utility inspection, weather depending.
- Typical scope: site clearing, grading and drainage, slab or pier prep, electrical service, water and sewer runs, and inspection sign-off.
- Price range: $45,000 – $130,000, with the spread driven by lot conditions and run lengths, not by finishes.
How we run ADU Site Prep & Utilities in Sunset, stage by stage

Here’s the sequence, and where you make decisions.
Stage 1 – Site walk and utility locate (day 1, 2 – 3 hours). We pull the county’s utility locate and walk the lot with you. You decide where the pad sits and how the unit is oriented. This is the stage where a bad siting decision gets caught cheaply. A 12-inch shift in the pad can avoid relocating an existing line that would otherwise add thousands.
Stage 2 – Clearing, grading and drainage (days 2 – 9). Vegetation comes out, the pad gets cut and compacted, and we set the drainage so water moves away from both the ADU and the main house. In Sunset’s flat lots, getting the fall right is the difference between a dry unit and one that takes on water during the June-to-November rainy season. You approve the drainage plan before we pour anything.
Stage 3 – Trenching and underground runs (days 9 – 20). Electrical conduit, water supply and sewer or drain lines get trenched and set to code depth. If the run has to cross existing concrete, drives or landscaping, that’s the moment you decide whether to bore under or cut and restore. Homeowners often pair this with Concrete Driveways & Concrete Work in Sunset when the trench crosses a driveway anyway, so the restoration and the new pour happen once.
Stage 4 – Electrical service and panel work (days 20 – 35). We set the meter, subpanel and grounding for the ADU, then coordinate the county inspection. If the existing service can’t carry the extra load, that’s a decision point: upgrade the main service or size the ADU to fit what’s there. This decision has the biggest price swing on the whole job.
Stage 5 – Final connections and inspection (days 35 – 50). Water and sewer get tied in, the slab or foundation prep is finished, and we walk the inspections through to sign-off. You get the signed inspection record and a written punch list before we call it done.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll make on ADU Site Prep & Utilities in Sunset
The spec decisions here are about durability and service life, not cosmetic taste.
- Slab-on-grade vs. raised or pier foundation. Slab is cheaper and faster, but it locks in drainage. A raised foundation costs more and gives you access to plumbing later. On Sunset’s flat lots, slab is the usual choice unless the grade says otherwise.
- Electrical service size. A 100-amp subpanel fits a small ADU; a 200-amp service upgrade costs more up front and leaves room for future load. Households planning a kitchenette, mini-split cooling and an EV charger should plan for the bigger service.
- Trench depth and conduit grade. PVC conduit in the trench outlasts direct-buried cable, especially where the soil stays damp. Worth the extra cost.
- Water supply material. PEX is standard and flexible; copper lasts longer but costs more. Moen and Delta fixtures are what we usually fit on the plumbing connections, and American Standard is common for the rough-in valves.
- Stormwater handling. A simple French drain handles most Sunset lots. A small retention area or dry well is warranted where the lot drains toward the house.
What ADU Site Prep & Utilities costs in Sunset, FL

The full package typically runs $45,000 – $130,000 in Sunset. That’s the number you’ll get in a written estimate, and the range is real, not a placeholder.
| Line item | Typical range |
|---|---|
| Site clearing, grading and drainage | $4,000 – $12,000 |
| Electrical service and panel work | $6,000 – $22,000 |
| Water and sewer runs | $6,000 – $25,000 |
| Foundation and slab prep | $8,000 – $28,000 |
| Inspection coordination and closeout | $2,000 – $6,000 |
The variables that push a job toward the top of the range:
- Distance from the meter and sewer tap. Every extra foot of run costs money, and a lot where the ADU sits at the back of the property can add $15,000 or more.
- Existing service condition. A panel that’s already near capacity means an upgrade, which is the single biggest swing.
- Lot drainage and soil. Poor drainage means engineering, extra fill and more trench time.
- Concrete cutting and restoration. Crossing a driveway or patio adds cost.
- Permit scope. Larger ADUs and utility upgrades add inspection steps and review time.
Written estimates from us are line-item and fixed. The number you see is the number you pay, with 0% financing for 18 months and $1,000 off projects over $10,000 available. What’s not included in a base site/utility estimate is the ADU structure itself – the design and permitting, the framing, the finishes. Those are separate scopes; see the wider Home Additions & ADU in Sunset page for how the full project fits together.
See the difference
Before
After
Before
After
Before
AfterWhat Sunset homes specifically do to this job
Sunset is a west-Kendall suburban community in unincorporated Miami-Dade (ZIP 33173), and the housing stock is mostly 1970s and 1980s single-family tracts with flat or low-pitch tile roofs and stucco-over-CBS block walls. That build era matters here for one reason: the county’s post-Andrew building code is the strictest in the country on wind-load, impact glazing and roof-to-wall tie-downs. When you add an ADU, the site and utility work has to meet today’s code, and the existing structure often gets pulled into that conversation because the utility tie-ins touch the main house’s system.
Practically, that means the electrical service at the main house gets reviewed against current standards during the utility inspection, and the tie-in point becomes a place where a 40-year recertification punch list can surface. We see it constantly on the older tracts off Sunset Drive and near the Kendall border – homes that are perfectly sound but where the original panel and the original lateral are at the end of their useful life. The subtropical climate adds to it: heavy summer rain and sun cycle stucco at the block joints, and flat-roof seams become chronic leak points, so drainage details around the new pad matter more than they would in a drier climate.
We cover this work across Sunset and the surrounding area, and we see a lot of properties where the pad and trench work has to respect mature trees, existing driveways and pool decks. That’s not a problem, but it’s a design input we account for from the first walkthrough.
Serving Sunset, FL – Our Local Coverage Area
We serve Sunset and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – ADU Site Prep & Utilities in Sunset

Plan on 6 – 14 weeks from permit approval to final utility inspection, with the longest stretches coming from county review and weather, not from the work itself. Call (888) 418-7102 for a timeline based on your lot.
Yes. In unincorporated Miami-Dade, electrical service, water and sewer connections and site grading all require permits and inspections. We pull the permits and walk the inspections through to sign-off as part of the job.
Usually yes, if the existing service has capacity and the trench path avoids the main house’s lines. The exception is when the existing panel is at capacity or the sewer tap needs to be relocated – that’s where the scope grows, and we’ll tell you that on the first visit, not the last.
The full package typically runs $45,000 – $130,000, with the biggest swings coming from electrical service upgrades, run distances and lot drainage. Call (888) 418-7102 for an exact quote – estimates are free.
Every project we complete is covered by our 730-Day Done Right Promise – if it’s not done right, we make it right. The utility connections and slab work carry the same coverage as the rest of the project.
Get a free estimate on ADU Site Prep & Utilities in Sunset
Call (888) 418-7102 to schedule a free on-site estimate. We’ll walk the lot, check the existing panel and utility taps, and give you a line-item written quote with the permit and inspection steps laid out. If the trench crosses a driveway, we can price Paver Driveways in Sunset alongside it so you’re not restoring concrete twice. Calls are answered by a live person 24/7, and the quote is fixed.
Written by the team at Groundwork Construction Co.