How Long Does Windows & Doors Take? Timelines and What to Expect
A single window takes under two hours to physically install. The permit process to do it legally in Miami-Dade can take three to six weeks. That gap – the space between how fast the work looks and how slow the paperwork runs – is where homeowner expectations and contractor timelines collide. In Hialeah, we’ve watched homeowners grow frustrated with crews over delays that were set in motion weeks earlier at a permitting counter. This guide breaks down the real calendar for window and door replacement in Hialeah: permit timelines by project scope, product lead times for NOA-compliant impact products, install time per opening, and what triggers an inspection hold. You’ll finish knowing exactly what each phase takes and how to plan around it.
Quick Answer
For a typical Hialeah window or door replacement, plan on four to twelve weeks from signed contract to final inspection. Most of that calendar is permit approval and product lead time, not installation. A full home re-window in Hialeah commonly runs six to ten weeks end to end, while a single impact door replacement can land closer to four weeks if the product is in stock and the permit moves cleanly.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
Table of Contents
- How Long Does the Permit Take in Miami-Dade?
- Product Lead Time for NOA-Compliant Impact Windows
- Physical Installation Time by Window Type
- What Triggers an Inspection Hold
- How We Sequence Multi-Window Projects
- The Full Calendar, Start to Finish
- Common Mistakes to Avoid
- Frequently Asked Questions
How Long Does the Permit Take in Miami-Dade?
Permit review for window and door replacement in Miami-Dade runs anywhere from two to six weeks depending on scope, completeness, and product documentation. The clock starts when a complete submittal lands, not when you sign a contract. A submittal missing a Notice of Acceptance (NOA) for one product can sit for days before anyone flags it.
Realistic calendar ranges by scope in Hialeah:
- Single window replacement: 2 to 3 weeks for permit review. Smaller submittals move faster through the intake queue.
- Two to five windows (typical partial replacement): 3 to 4 weeks. Reviewers often ask for clarifications on product approval or structural attachment.
- Full home re-window (6+ openings): 4 to 6 weeks. Larger scopes invite plan review comments and resubmittals.
- Door replacement (impact entry, sliding glass): 2 to 4 weeks. Door swaps are usually cleaner than window openings, but sliding glass doors can pull in structural review if the opening size changes.
Miami-Dade is strict because of wind-borne debris requirements. Every impact product must carry a valid NOA, and every install must match the approved installation method in the NOA. When a homeowner picks a product based on looks alone and the NOA doesn’t match the attachment detail for their block or stucco wall, review stalls. In Hialeah, we regularly see this with older homes in neighborhoods like Palm Springs and Hialeah Gardens, where original block construction predates modern window flashing standards. That’s not contractor delay – it’s design verification.
We pull the permit, submit the NOA packets, and track the review. What we can’t do is speed up the county’s queue. What we can do is submit a complete package the first time, which is the single biggest factor in hitting the lower end of those ranges.
Product Lead Time for NOA-Compliant Impact Windows
Product lead time is the second clock running in parallel with the permit. For standard-size impact windows, most manufacturers ship in 3 to 6 weeks. Custom sizes run 6 to 12 weeks, and casement or awning units with unusual configurations can stretch further.
Here’s the distinction homeowners miss: “standard size” doesn’t mean “fits your house.” A standard-size window ships faster because it’s an off-the-shelf production run. A custom size is fabricated to your rough opening measurements, which is why the lead time doubles. In older Hialeah homes where window openings were framed by hand decades ago, true standard sizes are rare – which is a big reason the lead time feels longer than the catalog suggests.
Availability varies by manufacturer and narrows during the spring and early summer storm-prep rush, when South Florida demand spikes ahead of hurricane season. Brands we source for window and door projects, including Andersen, Pella, and Marvin, have different current lead times by product line, and we confirm them at contract so the number you plan around is the number that holds.
One practical tip: order long-lead custom products the same week the permit is submitted, not after approval. Product lead time and permit review run concurrently. A six-week custom product and a four-week permit review done in parallel finish in six weeks – not ten. We sequence this deliberately on every Hialeah project, and it’s the single biggest difference between a smooth six-week job and a stalled ten-week one.
Physical Installation Time by Window Type
Install time is the part everyone underestimates in the other direction – it’s genuinely fast. A trained two-person crew can set, flash, and finish most openings in under two hours. Here’s what a reasonable crew day looks like per opening type.
- Single-hung impact window: 1.5 to 2 hours per opening. Fastest to install, common on second floors and smaller bedrooms.
- Impact casement: 2 to 2.5 hours per opening. Crank hardware and more complex flashing add time.
- Fixed picture window: 1 to 1.5 hours per opening. No operable hardware, simplest install.
- Impact entry door: 3 to 4 hours. Multi-point locking, threshold sealing, and stucco trim take longer than a window.
- Sliding glass door: 4 to 5 hours. Largest opening, heaviest product, most careful water management at the sill.
A realistic crew day for a two-person team is four to six window openings, or one to two door replacements plus a few windows. A full home re-window of 12 to 18 openings typically takes three to five working days of active install, spread across a week or two depending on inspection scheduling.
Stucco repair around frames is the variable that changes install time most in Hialeah. Homes built in the 1950s through 1970s with original stucco often need patching and re-finishing around each opening after the old frame comes out. That’s finishing work that follows the window install, and it’s a separate day in most schedules. We plan for it upfront rather than discovering it mid-job. Where the exterior lives, that repair work is a detail we handle in the same pass, and our Groundwork Construction Co. of Hialeah home page outlines how full-scope projects stay under one contract.
What Triggers an Inspection Hold
Passing the final inspection depends on what the inspector finds behind the wall. Several conditions in Hialeah habitually add days or weeks to a project, and none of them show up until the old window is out.
- Structural opening modifications: If the new window is a different size and the rough opening has to be enlarged or a header added, structural review and possibly an engineering letter come into play. This is the biggest source of holds.
- Stucco and frame condition: Rotted framing, cracked stucco, or missing flashing behind the old window turns a simple swap into repair work that must be completed and inspected before the window passes.
- Lintel work: On block construction, a compromised lintel above the opening can require repair, which means a structural component the original bid never touched.
- NOA mismatch at install: If the product installed doesn’t match the approved NOA or the installation method differs from the approved detail, the inspector flags it and the fix means re-doing the install to spec or resubmitting.
We handle these discoveries by working through them under the same permit and contract. Upfront pricing means the number you agreed to is the number you pay when we encounter standard-site conditions – no change-order games. If a genuine structural surprise turns up, you hear about it before any work continues, not on the final invoice.
How We Sequence Multi-Window Projects
A full home re-window in Hialeah doesn’t mean your house is a construction zone for a month. We sequence the work to keep most of the home livable, and we plan the sequence before a single product arrives.
- Group by elevation. We complete one side of the house at a time – front, back, then sides – so the exposure stays protected and the finished work reads as steady progress.
- Weather-dry every opening before moving on. Each opening gets flashed and sealed the same day, so a storm doesn’t catch an unfinished wall.
- One interior room at a time. Furniture stays where it is in most rooms. We cover floors, move what needs moving, and give you the day’s schedule the night before.
- Batch the stucco repair. Exterior patching is scheduled as a dedicated phase so the crew isn’t switching between install and finish all day.
- Schedule inspections early. We book the final inspection as soon as rough-in is complete, because inspector availability can add a week if you wait.
A realistic living plan: expect three to five working days of active install for a full home, spread over one to two weeks. Kids’ bedrooms get done first so sleeping stays undisturbed. Kitchens and main living spaces get scheduled around your routine – not the other way around. Background-checked, uniformed technicians arrive on schedule, and your questions during the project go to a real person, not a call center. You can reach us 24/7 when a scheduling question comes up mid-project.
The Full Calendar, Start to Finish
Here’s what the calendar actually looks like for a Hialeah window or door project, phase by phase. Ranges assume a straightforward scope with no structural discoveries.
- Estimate and product selection – 1 to 2 weeks. Choosing your product and confirming NOA details. We give you a written line-item quote so you see exactly what each window or door and its installation costs.
- Contract signing and permit submittal – day 1. Permit and product order go out the same week so both clocks run in parallel.
- Permit review – 2 to 6 weeks. Depends on scope and how complete the submittal is.
- Product lead time – 3 to 12 weeks. Runs concurrently with the permit; standard sizes finish first, custom finishes last.
- Install – 1 to 5 days. Based on opening count and type.
- Stucco and finish repair – 1 to 3 days. Often a separate phase after install.
- Final inspection – 3 to 10 days to schedule and pass. The last gate before the project closes.
Stack that up for a full home re-window in Hialeah: four to ten weeks typically, with custom products or structural surprises pushing toward twelve. A single window replacement often finishes in four to six weeks. Every project we complete carries the 730-Day Done Right Promise – if it’s not done right in the first two years, we make it right. That’s what “built to last, backed in writing” means on the finish line, not just the install day.
See the difference
Before
After
Before
After
Before
AfterCommon Mistakes to Avoid
- Expecting installation the week you sign. The gap between contract and install is the permit and product lead time. Homeowners who don’t plan for it end up frustrated with crews over delays set weeks earlier.
- Buying product before checking the NOA. A window without a valid Miami-Dade NOA can’t legally be permitted here. Picking by looks and confirming the NOA later is the most common cause of a stalled permit in Hialeah.
- Ordering product after permit approval. Custom products should be ordered the same week the permit is submitted, not after it’s approved. Doing them in sequence adds weeks to the job.
- Ignoring stucco repair in the budget. On older Hialeah homes, patching and refinishing around frames is real work. A bid that leaves it out comes in low and grows later.
- Skipping the final inspection to save time. Unpermitted window work can stall a future sale and complicate insurance after a storm. Always close the permit, even if it takes an extra week.
- Accepting a verbal estimate. A written line-item quote protects you when the scope changes mid-install. Vague bids are where change orders come from.
- Scheduling install during active storm warnings. A crew that can’t weather-dry openings the same day leaves the home exposed. We schedule around South Florida storm windows, and we don’t gamble with the forecast.
If your project touches more than windows – say a new fence or paver driveway around a re-window – the sequencing overlaps, and single-contractor coordination saves calendar time. We handle fence installation in Hialeah and driveway & pavers in Hialeah as well, so the exterior finishes tie together under one schedule and one warranty.
When to Call a Professional
Call a licensed professional whenever the project involves a permit, structural work, or impact-rated product. Miami-Dade window and door replacement is permit-required, and impact products must be installed to the approved NOA method to pass inspection. Structural opening changes, lintel work, and roof-line intersections on doors should never be a homeowner DIY project – they carry real risk and require inspection. If you’re considering an addition where new windows tie into new walls, that scope sits with a full-scope builder. Groundwork Construction Co. of Hialeah offers free estimates in Hialeah – call (888) 418-7102. You’ll get a written line-item quote, the permit pulled on your behalf, and the work backed in writing.
Frequently Asked Questions
Plan on six to ten weeks from signed contract to final inspection, or up to twelve if custom products are involved. For a home with twelve to eighteen openings, active install is three to five working days, with the rest of the calendar going to permit review and product lead time. Call (888) 418-7102 for a scope-specific timeline – estimates are free.
Yes. Standard-size impact windows usually ship in three to six weeks versus six to twelve weeks for custom sizes. The catch is that standard sizes only fit standard openings, and older Hialeah homes rarely have perfectly standard rough openings. We measure on the first visit so you know which category your home falls into before you commit.
Yes. Miami-Dade requires a permit for window and door replacement, and every impact product must carry a valid NOA. Unpermitted window work can complicate a future sale and an insurance claim after a storm. We pull the permit and manage every inspection on your behalf, and no project we complete leaves an open permit.
Because permit review is a county process, not a contractor process. Miami-Dade reviews NOA documentation, product approval, structural attachment details, and installation methods – a window submittal can sit in the queue for weeks. What a contractor controls is the completeness of the submittal. A complete package moves through review faster than a resubmitted one, which is why we confirm every NOA and attachment detail before we submit.
The biggest causes are structural opening modifications, stucco repair with hidden frame rot, lintel work on block walls, and NOA mismatches found at install. Any one of these can add a week or more. Groundwork handles standard-site conditions inside the contracted price – upfront pricing, no surprises – and flags genuine structural findings before work continues.
Yes. Every Groundwork technician is background-checked and arrives in uniform on every project. Our technicians have up to 12 years of experience with impact window and door installation in South Florida. Calls are answered by a live person 24/7, and you can call (888) 418-7102 with a scheduling question any time, day or night.
The Bottom Line

Window and door replacement in Hialeah is a four-to-twelve-week project in which install is the shortest phase. Permit review, NOA verification, and product lead time set the real calendar. A complete submittal, a product order placed the same week as the permit, and a crew that plans stucco repair upfront are what keep a project in the lower half of those ranges. If you’re planning a re-window, get the scope-specific timeline in writing before you sign. Groundwork Construction Co. of Hialeah gives you upfront pricing, a written line-item quote, the permit pulled and inspected, and the 730-Day Done Right Promise. Call (888) 418-7102 for a free estimate today.