Garage Conversion ADU in Olympia Heights: What It Takes and What It Costs
A garage conversion ADU in Olympia Heights typically runs $45,000 to $130,000 and takes 3 to 5 months from permit submission to final inspection. You’re turning an existing attached garage into a legal, self-contained living unit with its own kitchen, bathroom, sleeping area, and a separate entrance. In Olympia Heights, that means a county building permit, a new slab or floor system, plumbing and electrical brought up to code, and impact-rated glazing on any new opening. Call (888) 418-7102 for a free on-site estimate.
How We Build a Garage Conversion ADU, Stage by Stage

A conversion is mostly an interior rebuild inside an existing shell, so the sequence is tighter than a ground-up addition. Here’s the real order.
1. Feasibility walk and permit drawings (2 to 4 weeks)
We measure the slab, check the ceiling height (7 feet 3 inches is the practical floor for a habitable unit), and verify the garage isn’t the home’s only parking. This is where you decide the unit’s layout: studio or one-bedroom, kitchen placement, and where the new private entrance lands. Then we produce permit drawings for Miami-Dade County and submit. Because Olympia Heights is unincorporated, there’s no separate city review: the county handles everything. That’s one fewer gate, but the county’s turnaround is the long pole, so we file early.
2. Demo and structural prep (1 to 2 weeks)
Out come the garage door and opener, old shelving, and any drywall or insulation that’s failing. The old slab grade usually needs work. Most Olympia Heights garages sit a few inches below the house’s finish floor, and some slope toward the door for drainage. We correct that with a self-leveling topping or a new floor build-up. If the conversion needs a raised foundation or a new footing under a shared wall, that happens here. You approve the entrance location and the window plan before any framing closes up.
3. Rough-in: plumbing, electrical, HVAC (2 to 3 weeks)
This is the inspection-heavy stretch. The bathroom and kitchen are added to the building’s plumbing system, or served by a new slab-trench run. Electrical gets its own panel circuit, and the unit’s HVAC comes from a mini-split or an extension of the home’s system. A slab-on-grade garage in Olympia Heights makes trenching through concrete the single most disruptive step. In one Olympia Heights CBS house, we ran the bath line through an interior closet wall instead to spare a finished hallway, which cost a little more in carpentry and saved a week of concrete repair. You’ll choose fixtures and finishes at this stage or just before.
4. Insulation, drywall, and finishes (3 to 4 weeks)
The garage walls get insulated, the ceiling gets moisture-rated drywall, and the whole envelope gets sealed. In South Florida we don’t skip this: garages are the most humid space in the house, and an unsealed conversion glows with mold within a year. New impact windows and a door go in here, which is also when the exterior starts to match the main house. You sign off on paint, flooring, and cabinet style.
5. Final inspections and punch list (1 to 2 weeks)
Miami-Dade runs the final framing, electrical, plumbing, and building inspections. We walk the unit with you and close the punch list before you hand us the final check. The work is covered by our 730-Day Done Right Promise.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between
Every conversion has a handful of real forks in the road. These are the ones that move both the budget and how the unit lives.
- Floor system: A self-leveling concrete topping is the cheapest and most durable at roughly $2,000 to $5,000; a raised plywood-and-joist floor costs more but lets plumbing and ducting run underneath without trenching the slab. For a slab-on-grade 1960s garage, the raised floor often pays for itself in spared concrete work.
- Kitchen: A compact galley kitchen with a two-burner cooktop, under-counter fridge, and a real countertop runs $8,000 to $15,000. You can specify KraftMaid cabinetry if you want the same grade as the main house. A full-size range and dishwasher pushes it higher and screams “garage apartment” less.
- Bathroom: A walk-in shower and a 30- to 36-inch vanity handles most rentals; a tub adds about $2,000. Choose a vented exhaust that runs to the outside, not the attic, or the humidity stays.
- Windows and exterior door: Impact-rated units are the sensible pick in Olympia Heights. They hold up to hurricane-season wind, cut the sun load, and satisfy county product approval. They cost more than standard glass; you’ll thank yourself in June through November.
- Cooling: A mini-split is the most flexible for a single room-plus-bath. Extending the home’s system works only if the existing unit has capacity to spare, and a separate mini-split is usually the lower lifetime cost.
What a Garage Conversion ADU Costs in Olympia Heights, FL

The full range here is $45,000 to $130,000, depending on the garage, the finishes, and how much plumbing and electrical has to be brought in fresh. Here’s a look at the line items that drive that number.
| Line item | Typical range |
|---|---|
| Permit, drawings, and inspections | $2,500 – $6,000 |
| Demo, slab leveling, and floor system | $4,000 – $14,000 |
| Framing, drywall, insulation, and finishes | $12,000 – $32,000 |
| Plumbing and bathroom build-out | $8,000 – $20,000 |
| Electrical and panel work | $4,000 – $11,000 |
| HVAC (mini-split or extended system) | $4,000 – $9,000 |
| Impact windows, exterior door, siding touch-ups | $6,000 – $18,000 |
| Kitchen and finishes allowance | $8,000 – $20,000 |
What pushes a job to the top of that range: converting a garage that needs a new slab, moving the electrical panel, adding a second bathroom, or a detached-garage conversion where you’re also re-roofing and re-siding the building. What keeps it at the low end: a clean attached garage with an existing slab at grade, a compact kitchen, and simple finishes.
Our written line-item estimate covers the full scope: drawings, permits, inspections, materials, labor, and the offer stack. The number you see is the number you pay, and the job carries 0% financing for 18 months plus $1,000 off projects over $10,000. What it doesn’t cover is what you add later, like a fence around the unit’s entry, which homeowners often pair with our Concrete Driveways & Concrete Work in Olympia Heights or a privacy screen to be a proper entrance.
See the difference
Before
After
Before
After
Before
AfterWhat Olympia Heights Homes Specifically Do to This Job
Most conversions we do here start from a 1950s-to-1970s single-story concrete-block house. Those garages were never built to be living space. The walls are CMU block with furring strips, the ceiling height is usually fine, but the slab lacks a vapor barrier, and some have a step-down at the door threshold. The bigger reality is that Olympia Heights sits in unincorporated Miami-Dade, so your permit is a county permit, not a city one. The county’s post-Andrew wind-mitigation rules govern any new window, door, or structural tie you add, and every product has to carry the right approval. Many original homes in the 33165 ZIP also have flat or low-pitch roofs with minimal overhang, so a new entrance door and small canopy have to be detailed carefully against a wall that was never designed for water to roll off it. We work on occupied houses on tight lots here every week, so we stage materials out front, not across the neighbor’s yard.
This is part of a wider scope of work that we cover across Home Additions & ADU in Olympia Heights, but if your plan also touches the driveway or the yard, this is where our other trades come in.
Serving Olympia Heights, FL – Our Local Coverage Area
We serve Olympia Heights and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Olympia Heights

Allow 3 to 5 months from permit submission to final inspection. Plan for 2 to 4 weeks on drawing and permit review, then construction runs 8 to 12 weeks on a typical conversion. The county review is the wild card; we file early and keep it moving.
Yes. Any garage converted to habitable space requires a Miami-Dade County building permit and inspections. Skipping the permit can complicate your insurance, your resale, and any future code enforcement issue, so we pull it and pass every inspection before the job closes.
Sometimes. If the bathroom can back up to an existing plumbing wall or share the home’s main line without a long run, no slab work is needed. When the bathroom sits far from the house’s stack, trenching a slab-on-grade garage is unavoidable. We work out that layout during the walk, before you commit.
The range is $45,000 to $130,000, with a typical conversion landing near the middle. Finish grade, slab condition, and whether you need a new panel drive the number. Call (888) 418-7102 for an exact quote, and the estimate is free.
Every garage conversion we build is covered by our 730-Day Done Right Promise: if something isn’t done right, we make it right. You also get the county’s inspection sign-off, which is the paper trail a future buyer or lender will want to see.
Get a Free Estimate for Your Garage Conversion ADU in Olympia Heights
Call (888) 418-7102 for a free on-site estimate. A live person answers around the clock, so you won’t land in voicemail. We walk the garage, check the slab, look at where the plumbing and electrical will land, and then put a line-item number in writing. If your plans also include a new parking pad, homeowners often pair this with Asphalt Driveways & Resurfacing in Olympia Heights. See our Home Additions & ADU service for the wider scope, and find more about our coverage in Olympia Heights. Background-checked, uniformed technicians on every job.