New Detached ADU in Kendale Lakes, FL: What It Takes and What It Costs
A new detached ADU in Kendale Lakes typically runs $45,000 to $130,000 and takes four to eight months from first site visit to certificate of occupancy, depending on size, utility runs, and how fast Miami-Dade County moves your permits. The structure is separate from the main house, so you’re building a second small home on your lot: foundation, roof, electrical service, plumbing, and impact-rated openings. Call (888) 418-7102 and we’ll walk your lot and give you a written, line-item number before you commit to anything.
How the Job Actually Runs, Stage by Stage

Most homeowners want to know what happens when, so here’s the honest sequence we follow on a detached ADU in Kendale Lakes.
Stage 1: Lot walk and feasibility (week one)
We measure your setbacks, check where the sewer lateral or septic sits, and confirm the ADU footprint fits within county zoning for your lot. You decide the size and where it goes. This is also when we flag anything the 40-year recertification record shows about your main house, since utility tie-ins touch the existing structure.
Stage 2: Design and permitting (weeks two through ten, sometimes longer)
Drawings go to Miami-Dade County for building, zoning, and utility review. You’ll be making finish decisions here, not on the fly later. Expect the permit clock to be the longest single stretch of the project; county review timelines move, and we plan around them rather than promising a date we don’t control.
Stage 3: Site prep and foundation (two to three weeks)
Grading, drainage, and the slab or stem-wall foundation go in first. South Florida’s summer downpours mean we grade away from the structure and set drainage before we pour, not after. A separate concrete pad or approach often gets built at this stage; homeowners frequently pair this with Concrete Driveways & Concrete Work in Kendale Lakes so the ADU has its own walkway and parking without tearing up the yard twice.
Stage 4: Structure, roof, and rough-ins (six to ten weeks)
Walls go up, the roof goes on, and electrical, plumbing, and HVAC rough-ins get inspected before anything is closed in. You decide window and door specs here. This is the stage where the wind-mitigation details that matter in hurricane season get locked in.
Stage 5: Finishes and final inspection (four to six weeks)
Drywall, flooring, cabinets, fixtures, and paint, then the final county inspection and certificate of occupancy. You’ll walk the finished unit with us before we call it done. Everything we build carries the 730-Day Done Right Promise, so if something isn’t right after move-in, we come back and make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Shape Your ADU
Every detached ADU in Kendale Lakes comes down to a handful of decisions. Here’s what you’re really picking between.
- Size and layout: A one-bedroom studio in the 400 to 600 square foot range keeps you near the low end. A two-bedroom around 700 to 900 square feet pushes toward the top. Bigger footprint means more foundation, more roof, more everything.
- Impact-rated openings: In this wind zone, impact windows and doors are the smart default. They cost more up front than standard units but skip the shutter routine every storm and protect the structure. You can choose a mix of impact glass and rated doors to manage budget.
- Roof assembly: Shingle is the common, cost-effective choice. Standing-seam metal lasts longer and sheds rain better but adds cost. Either way, the flashing and roof-to-wall connections are where water gets in if they’re rushed.
- Fixtures and finishes: We use established brands like Moen and Delta for faucets and American Standard for fixtures because parts are available locally and hold up. You can upgrade to a soaking tub or a nicer vanity, but keep the plumbing in one wall and you save real money.
- Utilities: Tying into the main house service is usually cheaper than a separate meter. A separate electrical service or a long sewer run is one of the biggest swing factors in the price.
What a New Detached ADU Costs in Kendale Lakes, FL

Plan on $45,000 to $130,000 for a detached ADU in Kendale Lakes, with most projects landing in the $70,000 to $110,000 range once utilities and finishes are counted.
Four things push the number up or down:
- Size and complexity: Square footage drives materials. A simple rectangular footprint costs less than an L-shape with more corners and roof planes.
- Utility distance: The farther the ADU sits from your main electrical panel and sewer line, the more trenching, conduit, and labor you pay for.
- Site conditions: Grading, drainage, and soil work add cost when the lot slopes or drains poorly, which is common on older Kendale Lakes lots.
- Finish level: Builder-grade finishes sit at the low end; upgraded kitchens and baths move you toward the top.
Your written estimate spells out foundation, framing, roof, windows, rough-ins, finishes, permits, and inspection fees line by line. What it won’t include unless we list it: landscaping restoration, a separate driveway or patio, and furniture or appliances you supply yourself. The number you see is the number you pay, and we offer 0% financing for 18 months plus $1,000 off projects over $10,000.
See the difference
Before
After
Before
After
Before
AfterWhat Kendale Lakes Homes Specifically Do to This Job
Kendale Lakes is a built-out 1970s and 1980s Kendall suburb, so a detached ADU here is almost always an infill project on a lot that already has a house, a driveway, and mature landscaping. That changes the work. The typical home is CBS block with stucco and a barrel-tile or shingle roof, and stucco-over-block walls routinely hide hairline cracks and moisture that only surface at the county’s 40-year recertification. Any exterior change near those walls often needs both a Miami-Dade County permit and HOA approval before the first block is laid, so we check both up front rather than mid-build.
The climate shapes the build too: intense sun, heavy summer thunderstorms, and hurricane-season wind-driven rain mean impact-rated openings, tie-downs, and drainage that holds up to downpours are not optional. Homes around the 33183 ZIP and along the Kendall corridors sit on lots where setbacks and utility locations decide the footprint, so the first visit is as much about what the county allows as what you want.
Serving Kendale Lakes, FL – Our Local Coverage Area
We serve Kendale Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Kendale Lakes

Four to eight months from start to certificate of occupancy, with permitting often the longest stretch. Construction itself runs three to five months once the county issues the permit. Call (888) 418-7102 for a timeline based on your lot.
Yes. Miami-Dade County requires building, zoning, and utility permits, and most HOA communities need separate approval. We pull the permits and coordinate inspections; you don’t handle the paperwork.
Usually yes, if the ADU ties into the main service with a reasonable run. Long sewer or electrical distances add cost. We confirm this on the first visit before you commit.
Most projects run $45,000 to $130,000, with the typical build in the $70,000 to $110,000 range. Size, utility distance, site conditions, and finish level set the final number. Call (888) 418-7102 for a free line-item estimate.
Every ADU we build carries the 730-Day Done Right Promise: if it’s not done right, we make it right. Background-checked, uniformed technicians handle the job, and calls are answered by a live person 24/7.
Get a Free Estimate for Your Detached ADU
Planning a new detached ADU in Kendale Lakes? Call (888) 418-7102 for a free on-site estimate. A live person answers around the clock. We’ll check setbacks, utility locations, and HOA rules, then hand you a written line-item quote with no surprises. It’s part of our broader Home Additions & ADU work, and if you’re weighing a larger project, see our Home Additions & ADU in Kendale Lakes page or our coverage across Kendale Lakes. Many clients also pair this with Paver Driveways in Kendale Lakes for the ADU’s own approach.